2025-06-02 • No comments • • Regeneration Capital Grant Fund
1 What do we want to do?
Tobermory Fisherman's Pier Association intends to renovate and improve Thomas Telford's hisoric pier for the use of fishermen and other commercial users. We would like to preserve the pier as a place that can be used and enjoyed by locals and visitors alike. We want to open the pier to other commercial users and provide a solution to the risk of flooding caused by increasingly higher tides. A structural engineers report has been commissioned and has provided a plan for remedial works.
2 Why is the project needed?
While the pier is a vital economic resource for the fishermen of North Mull, it is also an essential and integral part of Tobermory's built heritage. Without the pier the fishermen would need to look for alternative space to store and repair gear. They would have to use moorings or pontoons and they would have to use alternative means to land their catch. All of these alternatives are costly, inconvenient and not as safe as the platform provided by the pier.
We have the support of the community and are backed by Mull Community Council, Tobermory Harbour Association and Mull and Iona Community Trust.
3 What positive changes will our project bring about?
The proposed improvements to the pier will provide a fit for purpose structure that will enable the fishing community, and other commercial users, to have confidence in the long-term viability of their businesses and provide the oppurtunity to support new entrants to the sector. Securing the long-term future of the pier will enable it to remain at the heart of the community for centuries to come, bringing economic benefit to the town as a platform for the fishermen and also as part of what draws visitors to Tobermory. It will continue to be a much loved hub for community celebrations and a valued civic space for locals and visitors to enjoy.
4 How long will our project run for?
The project will start in March 2026 and run for seven months.
Please refer to the attached PDF file for our more comprehensive proposal.

"On your Bike", Tayinloan Youth Club
2025-04-29 • No comments • • Regeneration Capital Grant Fund
1. First and foremost, we want to keep our children safe while they enjoy being outdoors. The A83 runs the entire length of West Kintyre and as all the villages are spurs from this extremely fast and dangerous road, there is just nowhere safe for children to ride their bikes. To address this, we wish to install a pump track at Tayinloan
2. We feel it is needed because the main A83 is getting busier, and is one of the most dangerous roads in Scotland. Children and adults of all ages are now taking up more and more physical exercise and cycling has become very popular indeed. We wish to offer a safe enclosed area where they can learn and ride in safety.
3. The project could bring many positive benefits. Pump track riding not only provides a physical workout, but also promotes good mental well-being. It’s not just about the physical challenge – although that’s definitely a big part of the appeal. Spending time outdoors, surrounded by nature, has a way of melting away stress and lifting spirits. Pump track riding can actually help sharpen the mind and improve cognitive function. It is a way to encourage youngsters to leave their screens for a while and enjoy outdoor activities and social interaction.
These are just some of the positive changes for those participating in the sport. However there are many others, such as helping with social isolation which has become a big problem in these post Covid times.
At the pump track, generations come together, no matter their age! From little ones with their parents or grandparents to teenagers and young adults, everyone can enjoy fun and friendship, making it a true community hub. The little ones learn how to ride and gain confidence, while the more experienced riders practice their skills. Parents can have a great time too, as they watch their children gain confidence and make friends
4. Once the planning has been approved (hopefully within 6 months of application) and the funding secured, the pump track can be installed in 6 weeks.
We will work with Velosolutions, who are world leaders in this technology.
We will also liaise with schools and youth clubs.
We will work with Argyll and Bute Councillors

South Kintyre Growing Project
2025-05-29 • No comments • • Regeneration Capital Grant Fund
SKDT already operates the gateway garden (under licence from ACHA), as well as the putting green and herb garden (under licence from ABC) and the Robert Black Memorial Helipad (owner operator).
SKDT has well developed plans in place for these areas, which we would obviously like to see being well used by the community.
The creation of the Gateway Garden over the last 18 months has provided opportunities for food growing, education and intergenerational activity which are identified actions in the Campbeltown Community Action Plan (2022 – 2027). The Growing Project will also go some way towards developing local resilience and food security.
The initial redevelopment of the Gateway Garden, which is in a prominent location at the entrance to the town, has given impetus to other volunteers and potential gardeners to come forward.
Unfortunately, the limited size of the current garden area has restricted the number of growing plots available. The Growing Project would allow us to identify other suitable growing areas which we can develop in a gradual and progressive way, The, now ceased, Campbeltown Community Garden has donated their remaining plant and equipment to SKDT, now in storage, which will give us a head start in developing new growing spaces.
We also have a large selection of lawnmowers, gardening tools, hoses and other items which we can use for this project. However we will still need to acquire additional equipment and sundries (gloves, boots, compost, fertiliser etc) to allow us to proceed.
We will look to access additional funding to develop the project further via local funding through e.g. Common Good Fund, MACC and Campbeltown Community Windfarm Fund.
The main focus of this expansive project will be to attract, retain and train volunteers to get their hands dirty and get digging, weeding and planting.
As well as our own volunteers, there is another group of volunteers who have been looking after the bus terminal area. We will work alongside and support both of these groups. We will access additional training and advice from a network of community gardens throughout Scotland.
We would also continue and expand our work with the local schools on developing their own gardens and teaching kids the benefits of growing your own food. This would also allow for some important intergenerational activities which improve the lives of young and old.
We will also support and lobby for the provision of allotments for people to grow their own produce.
Clachan Village Hall/Community Hub Phoenix project
2025-06-02 • No comments • • Regeneration Capital Grant Fund
Clachan lost its much loved and well used village hall due to terminal decline as an asbestos concrete roofed building with corroded portal flames and was demolished in 2022. The iconic historic B Lited Kilcalmonell church was purchased with a Scottish Land Fund grant to serve as a replacement village hall to arise like the proverbial phoenix from the ashes of the old hall. The hub will allow resumption of the dormant user group activities and will provide a recreational, educational venue for the comunity as well as a resource for private hire. It will also serve as an emergency centre to provide safe haven and meal provision at times of emergency such as has occured on many occasions over the past 10 years particualrly in relation to power cuts, village floods, a freak snow storm, and gales, some of which also resulted in blocking the A83 artery to Campbeltown. We are in the process of renovating the exisitng church building to provide the main comunal space and this work shold be completed by the end of the year. This is being funded in part by are own fund raising initiatives and by local wind farm trust grants. We then need grant funding for the extension to provides the addtional space for : a catering/kitchen area, a small meeting room, additional storage and toilet provision with disabled access for larger capacity events and activities. It is is this extension project (phase 2) that we are seeking funding from the RCGF scheme as well as other agencies such as the Windfarm Trusts, and other grant funders. We are looking for this construction work to be done 2026-2027.
Tiree & Coll Community Vet Practice Project
2025-05-30 • No comments • • Regeneration Capital Grant Fund
What do we want to do?
This project seeks to transform an existing community space at the Tiree Rural Centre – previously used as a café – into a community-owned vet practice serving the islands of Coll and Tiree. The Rural Centre hosts the island’s cattle and sheep market along with an exhibition showing all aspects of crofting and wildlife on Tiree. It plays a leading role in preserving Tiree’s rich crofting heritage and, together with its central location on the island, is well-placed to host a community vet practice. This represents a significant investment and regeneration project for both Tiree and Coll, and would contribute positively to local economies, which revolve around crofting.
This project is led by a consortium of island stakeholders which includes Tiree Rural Development (which manage the Rural Centre), Tiree Community Development Trust, various crofters and community representatives, and the current vet. This steering group provides strategic oversight and represents a community-led approach focused on safeguarding a key island service and a shared belief that something must be done before it is too late.
To that end, the Tiree Community Development Trust commissioned a feasibility study to investigate renovating the available, currently vacant space at the Rural Centre into a vet practice. With a full design and accurate costs now in place, the consortium are now in a position to commence a build phase of the project, and are actively seeking funding to make this important project a reality.
Why is our project needed?
A vet is absolutely critical to both Tiree and Coll. Without an island vet, crofting largely becomes untenable, as crofters need access to veterinary services to keep animals and ensure their welfare. Crucially, Tiree’s culture, history, economy, and its unique machair landscape are all strongly linked to crofting. In addition to running their crofts, crofters often hold multiple jobs and community roles, and are essential to island life.
As crofting is the island’s primary industry, the loss of a vet would have dire consequences for the local economy. This would likely lead to emigration and a decline in the numbers of families living on the island. Even a few families leaving would have a significant impact on services, and could spark the further closure of lifeline services such as the school, GP surgery, and local businesses – a gradual process often seen in other small Scottish islands once the population falls below a critical point. Once these key services are lost, we know from experience and research that they rarely return. This is due to the high cost of running services on islands, the challenges of setting up, and the dwindling economic returns and economies of scale. Remote islands are places where market failure is the norm, not the exception. The group recognises that the vet practice is one such service that the island cannot afford to lose.
Moreover, many residents keep small animals and pets; the operational and cost implications of relying on a mainland vet service for Tiree and Coll residents are significant, in some instances prohibitive. The vet also plays a central role in protecting the island’s unique wildlife and marine life, regularly attending call-outs to help stranded dolphins and seals, for example.
With our current vet looking to retire in the near future, we are keen to minimise barriers that an incoming vet faces. In the past, it has been difficult to recruit and retain vet capacity, and recent shortages in the sector, combined with a low financial return of investing in an island-based vet practice, have made this challenge more acute. Additionally, the current vet operates out of a small and temporary space which is unlikely to meet future RCVS standards and does not fully meet the dynamic needs of an island vet. A high-quality, affordable, and long-term practice ensures that the prospect of moving to Tiree to take over the practice becomes much more attractive and financially viable.
What positive changes will our project bring about?
This project provides key benefits to crofters and the wider community on both Tiree and Coll:
- A bespoke, compliant, and modern vet practice will make it easier to attract an incoming vet to the island, and retain them once they have arrived.
- It improves the standard of care and contributes positively to animal welfare, as well as providing a better space for a vet to operate out of.
- Securing an appropriate practice space for Tiree and Coll safeguards the entire crofting sector, the island’s primary industry.
- Security of tenure for the vet, as well as a stable rental income for a community group dedicated to improving conditions for crofters and wildlife on Tiree.
- Making better use of existing assets, and optimising design to factor in environmental improvements.
- Tiree and Coll pet owners are guaranteed access to veterinary care without having to rely on mainland services, which can be difficult and expensive to access – especially during emergencies.
- The project contributes to the wider regeneration of Tiree’s existing community-owned assets, and will play a key role in Tiree Rural Centre’s future.
- A lifeline island service is maintained, contributing to the overall viability of Tiree’s small, unique, and thriving community.
How long will our project run for?
The project will start on: 01/03/2026
The project will run for : 12 months
.jpg)
Complete our lifeline link road!
2025-06-02 • No comments • • Regeneration Capital Grant Fund
In 2021 and 2022, IKDT secured funding to construst 1.79KM of brand new road connecting the North and South of the island. This project has been in the pipeline for many decades and has connected up the two different communities and is allowing our island to thrive as one. Just after we have secured the funding for the 2nd stage of the project, the tar topping, war broke out in Ukraine. Apart from the obvious humanitarian crisis, this had an instant impact on the price of all the raw materials required for surfacing. It meant we had to scale stage 2 back and make do with tarring the new built section of the road with a single layer of tar and leave approx 500 metres of road in an unbound, farm track state. Our plan for stage 2 had been to deliver 2 layers of tar over the new road (1.79km) and the 500m of existing road when we could petition the council to adopt the road as it connects up the existing council road to several council tax paying households. As it stands, while the road is in use and is hugely beneficial to life on the island however the maintenance burden on IKDT is not ideal. The council will not consider adoption until the road is brought up to the standard we had planned for stage 2 so we are hoping to complete the job. Adoption is key to the long term future of the road and indeed to whole community as it will allow unfettered access to all including vital services, emergency vehicles and access to the lifeline ferry service. The surfacing could be delivered in one week but the effects would be felt for generations to come. We would hope to continue the excellent working relationship with A&B Roads department to help deliver the best value for money possible.

Dunoon Pier
2025-03-26 • No comments • • Regeneration Capital Grant Fund
Operating under the governance of the Dunoon Community Development Trust and in partnership with Argyll and Bute Council, the Save the Pier working group has been actively seeking funding and carrying out further research to progress the necessary technical studies needed to inform these types of developments.
The initial goal of the working group is to develop a robust, evidence-based feasibility study, providing a clear case for the pier’s redevelopment and its potential role within the future of the town’s wider marine infrastructure. Longer-term they hope to begin the process of the pier’s renovation.
The wider team —comprising volunteers with expertise in public sector infrastructure, finance, heritage preservation, project development and community engagement —has been engaging with stakeholders in the public and private sector, having discussions with potential funders, and laying the groundwork to ensure any future redevelopment is viable and sustainable.
Our Progress So Far
The project has involved extensive positive collaboration with Argyll and Bute Council, alongside wider stakeholder consultations, a public petition, and collaboration with advisors in major infrastructure, heritage conservation, and funding options.
Community Involvement
Community engagement will be essential to shaping the pier’s future. There has consistently been a lot of interest on social media and in the newspaper with large numbers of people getting behind the idea of Dunoon Pier being regenerated. It is clear that there is good community support for the idea and the working group welcomes the input of local residents, businesses, and local organisations as the project evolves.
At this stage, the focus is on gathering the necessary technical and financial evidence to determine what is achievable.
Next Steps
Funding is currently being secured to complete a feasibility study, which will provide a comprehensive assessment of the pier’s future potential. This study will form the foundation for securing funding to progress any future redevelopment. However, given the scale of the project, careful planning and a phased approach is required. We aim to complete this initial phase and be in a position to share the feasibility study by Summer 2025.
Looking Ahead
Public infrastructure projects of this scale take time, but the dedication of the team working with the support of the local authority and Dunoon Community Development Trust means that there is a good chance that this project will progress positively. The Dunoon Pier working group is committed to communicating on their progress and will provide regular updates via Dunoon Community Development Trust and partners as the project moves forward.

From Small Seeds - Cornabus Community Forest Initiative
2025-05-08 • No comments • • Regeneration Capital Grant Fund
IDI has set aside an initial 25 acres of Cornabus Community Forest to deliver housing, a Community Orchard, Garden and allotments for the community.
In 2021 we carried out extensive consultation on the proposed development site within the now community owned Cornabus Forest. Formerly a commercial Sitka Spruce plantation, the whole site will eventually be replanted with native broadleaf to replicate the Atlantic Rainforest once prevalent on Islay, delivering significant biodiversity benefits but also on the community wish list from the consultation was housing for young people, allotments, an orchard and forest trails and a garden areas.
The project will endeavour to add social and environmental value to the site and also create a space for community members and groups to enjoy. In 2020 Islay lost it's well-known community garden at Islay House, due to the property being sold on the open market. This was a much loved and used community space. Although the site at Cornabus is not a walled garden, extensive research on other forest garden initiatives was carried out in 2022 - including visits to Royal Botanical Society managed forests and formal garden spaces, such as Benmore and Puck's Glen. The intention is to take some elements of the old community garden site and duplicate them and the new, with lots of additional features.
The project is highly ambitious, and the first stage of funding has been secured from Inspiring Scotland for development of the tree nursery site where we will grow the replacement trees. Secondary funding has come from Carbon Neutral Islands, specifically to create some of the infrastructure and assist with a circular economy approach to fuel wood supply on the island at affordable rates.
This is a lifetime legacy project that will create a destination for outdoor enjoyment but also offer a range of solutions to the socio-economic challenges that the island faces with a strong focus on becoming Carbon Neutral. Islay is in a housing crisis and the addition of 10 affordable houses will help address some of those issues. To ease pressure on the Grid, the project also comes with it’s own district heating system using the remaining Sitka Spruce on site as a fuel source, a wind turbine and solar panels.
The finished project will deliver a host of positive benefits including but not limited to:
- Employment
- Affordable Housing
- Circular Economy approach/local fuel
- Community garden
- Allotments
- Carbon capture in new tree planting
- Significant destination space for locals and visitors alike.
The project will link into Argyll College, Islay High School, Youth Initiative and employability. Partners and funders will be Scottish Government – Rural and Islands Housing Fund, Argyll and Bute Council and National Lottery. Community group usage will be open to all groups on the island and will link into national networks such as Community Woodlands Association, Scottish Islands Federation and Community Tree Nursery Network.

Tarbert Harbour Watercraft Launch & Recovery Slipway and Community Activity Hub
2025-04-09 • No comments • • Regeneration Capital Grant Fund
-
Tarbert Harbour Authority has a bold and strategic ambition to build a Launch and Recovery Sportscraft / Watersports Slipway together with a Community and Watersports Activity Hub. Whilst the Activity Hub and Slipway are linked as a strategic development; for the purposes of funding, build and project managment, they are being treated as distinct projects with individual costs, individual project timescales and individual benefits and outcome profiles. Phase 1 will see the development of a Watercraft Launch & Recovery Slipway, Kayak Pontoon and Boat Laydown Area - £1.5M Phase 2 will see the building of a Community Water Sports and Activity Hub - £1.4M.
-
The Project utilises a vacant and semi-derelict harbourside development plot to address: A significant health and social gap in terms of water sports, gym and soft play areas and associated learning and development activities. An identified need for orgnanised, safe, educational and affordable access to the above facilities together with a learning area, meeting and events space. Community Facilities are vital for the well-being of rural villages and a community hub/gym combined with a water sports facility can be a game-changer for diverse groups of people. The integration of these amenities not only promotes physical health but also fosters social interaction together with economic growth.
-
The development of the Community Water Sports Slipway and Activity Hub will provide wide ranging benefits. Adults and children in Tarbert and Loch Fyne's local communities will have accessible opportunites to improve their health, wellbeing, social confidence, learning and skill sets. Local families will benefit from access to safe soft play and early years development stimulus. Young people in education along Loch Fyne will have the opportunity to acquire new experiences, skills and qualifications that will support their social development and provide a platform for demonstrating their capabilities in diverse ways. Visitors to Tarbert and the surrounding area, whether for work or leisure purposes, will be able to relax and participate in safe gym exercise, supervised water-based activities, training and development in sailing and boating to established National Standards. Additional employment opportunities will be directly and indirectly created by this development. The development will be a major step forward in realising the next stage in the village's regeneration and development. Regular exercise is known to reduce stress, anxiety and depression, leading to healthier, more product individuals. A well equipped gym provides access to fitness resources, encouraging users to adopt a healthy lifestyle. The gym will cater for a wide range of fitness levels and interests, from beginners to advanced. The Activity Hub will also be used as a training/meeting place for sports clubs/organisations, community groups, school groups, RYA training, activity leaders, famiies and friends.
-
It is proposed, once all Phase 1 funding is in place, to commence the development of the Launch/Retrieval Watercraft slipway this financial year with a completion date of mid 2026, Phase 2 will follow, when funding allows, and when the final funding matrix is clearer.
Partnerships: We plan to collaborate with:
-
Argyll & Bute community Council to align with local interests.
-
Schools and educational institutions to promote learning opportunities.
-
Local businesses, including bike hire providers and tourism boards, to enhance visitor engagement.

Renewing the fabric of Atlantis Leisure for the next Generation
2025-06-02 • No comments • • Regeneration Capital Grant Fund
Atlantis Leisure is a vibrant, community-run health and wellbeing hub in the heart of Oban. For over 30 years, we’ve been a lifeline for locals of all ages - a place where toddlers learn to swim, teens train with sports clubs, adults improve their fitness and older residents stay active and connected. As a registered charity and social enterprise, every penny we earn is reinvested. Our huge range of facilities are designed to support active, healthy lives. We work with schools, NHS partners, and community groups to deliver inclusive, high-impact services. With over 150,000 visits a year and no other facility like it for 95 miles, Atlantis isn’t just a leisure centre - it’s the beating heart of our community.
This application comprises separate projects that are also listed on Aspiring Places indivdiually but we thought it made sense to group them together as a single proposal for the purposes of RCGF too:
1. What do you want to do? We propose a multi-strand capital regeneration programme at Atlantis Leisure — a vital, community-owned asset serving Oban and surrounding remote rural areas — to deliver large-scale, community-led change aligned with RCGF's aims that breathes new life into an over 50 year old facility.
This project brings together three deliverable, community-prioritised infrastructure improvements:
- Installation of rooftop solar panels and battery storage: significanty reducing carbon emissions, lowering long-term operating costs and contributing to Net Zero targets. 160k
- Expansion of Atlantis’ gym: a two-storey extension to accommodate growing community demand, support inclusive programmes like Elevate & Stay Active, and provide flexible meeting and office space to host outreach services and community partners. 175k
- Creation of accessible changing facility: reconfiguring existing internal space, to provide a dignified, fully inclusive changing area to support disabled users 50k
- Restoration of end of life outdoor sports pitch: bringing an end-of-life, unusable asset back into service, enabling schools, clubs, and informal groups to use it year-round, relieving pressure from indoor space and boosting physical activity levels. 90k
- Restoration of Sports Hall Roof: rectifying end-of-life aspects of the roofing. 150,000k
2. Why is your project needed? Atlantis Leisure is a community-run registered charity and social enterprise that delivers year-round access to sport, physical activity, and wellbeing services. We are the only such facility within a 95-mile radius and serve over 150,000 users annually — yet key parts of our infrastructure are now limiting access, affordability, and impact.
- The pitch is end-of-life and unusable, with back-up facilities constrained by a statutory noise order.
- We've run out of room in our existing gym facility meaning vital communtiy programmes like Healthy Options are unable to operate properly
- There is no suitable changing space for users with complex access needs, meaning many are excluded from participation.
- Energy costs are surging, making it harder to deliver affordable access and sustain services for low-income families.
The project will regenerate these essential community assets, futureproof our building, reduce inequalities in access, and enable Atlantis to deliver sustainable social value for decades to come — directly supporting the RCGF’s priorities around deprivation, climate, inclusion, and place-based transformation.
3. What positive changes will your project bring about?
- Inclusive Infrastructure: The accessible changing space addresses long-standing inequality, empowering disabled users to participate fully & independently.
- Net-Zero Progress: Solar & battery systems will directly reduce carbon emissions, support national climate goals, & make Atlantis more financially sustainable.
- Renewed Community Space: The front pitch transformation will reinstate valuable outdoor capacity, expanding options for schools, clubs, and families.
- Address Capacity Issues: Expanding the gym answers a growing problem with existing capacity.
- Child Poverty Impact: Reducing running costs helps us to maintain subsidised programmes, removing financial barriers to physical & social wellbeing.
- Place-Based Renewal: This project aligns with the Place Principle and National Strategy for Economic Transformation by investing in a community-anchored asset with cross-cutting impact.
Together, these outcomes represent transformational, community-led regeneration that will enhance the resilience, health, and wellbeing of Oban.
4. How long will your project run for?
The project is fully deliverable within FY 2026–27.
- Start: Early 2026
- End: March 2027
- Drawdown Ready: All spend will be committed or completed within the terms of the RCGF.
- Delivery Approach: Projects will be managed by Atlantis Leisure’s Facilities Subgroup with oversight from the Board.
- Match Funding: Confirmed: Atlantis own contribution. Pending: we are actively pursuing applications and conversations with other funders including LES's CARES programme