Community Village Hall/Community Hub

Clachan Village Hall/Community Hub Phoenix project

2025-06-02  •  No comments  •  Clachan Village Hall (Kintyre) SCIO SC050324  •  Regeneration Capital Grant Fund

Clachan lost its much loved and well used village hall due to terminal decline as an asbestos concrete roofed building with corroded portal flames and was demolished in 2022. The iconic historic B Lited Kilcalmonell church was purchased with a Scottish Land Fund grant to serve as a replacement village hall to arise like the proverbial phoenix from the ashes of the old hall. The hub will allow resumption of the dormant user group activities and will provide a recreational, educational venue for the comunity as well as a resource for private hire. It will also serve as an emergency centre to provide safe haven and meal provision at times of emergency such as has occured on many occasions over the past 10 years particualrly in relation to power cuts, village floods, a freak snow storm, and gales, some of which also resulted in blocking the A83 artery to Campbeltown. We are in the process of renovating the exisitng church building to provide the main comunal space and this work shold be completed by the end of the year.  This is being funded in part by are own fund raising initiatives and by local wind farm trust grants. We then need grant funding for the extension to provides the addtional space for : a catering/kitchen area, a small meeting room, additional storage and toilet provision with disabled access for larger capacity events and activities. It is is this extension project (phase 2) that we are seeking funding from the RCGF scheme as well as other agencies such as the Windfarm Trusts, and other grant funders. We are looking for this construction work to be done 2026-2027.

No supports
The petrol station in busier days.

Tighnabruaich Community Petrol Station - powering a fragile community

2025-05-31  •  No comments  •  Tighnabruaich District Development Trust  •  Regeneration Capital Grant Fund

The Problem

Our petrol station is threatened with closure due to retirement of the owners, and the business case for a commercial purchase is very weak. We are likely to end up with no fuel within 24 miles (and more for the isolated parts of our district). If people are forced to travel out of the area for fuel, they will tend to do all their shopping on the same trip, affecting other local shops and businesses . Carbon emissions will increase as people are forced to travel at least 48 miles round trip for fuel, over single-track mountain roads. Even running garden tools will become problematic, and our local Life Boat and volunteer Fire Service will have problems with adequate supply.

The Solution

This type of scenario is a perfect fit for a community enterprise response: improving the resilience and sustainability of the local area; providing opportunities for business and employment; and helping our community plan ahead for the switch to electric vehicles. We need a community-owned petrol station to secure fuel supplies in the area in the medium-term, install charging points, create business units for rent, and refurbish the historic building as a community transport and resilience hub. Having run two community consultations in the past two years we know that people will continue to need fuel for the next 10 - 15 years, that there is demand for workshop spaces for small businesses and that the petrol station building (a former Victorian pier house) has a high heritage value for the local community.

Opportunities

Since consulting on the community purchase of the petrol station, we have a had two direct approaches from potential workshop tenants. One local community group has a waiting list of small businesses looking for premises, so the creation of new work units would have a positive impact on the local economy. With joint support from the Scottish Land Fund we would be able to employ a Project and Transition Manager, tasked with delivering improvements to the building, installation of charging points and other renewables measures, managing the workshop spaces and developing our plans for electric community transport. We see many benefits arising from this project as well as securing a vital service.

Current Stage of Planning

We are about to apply to the Scottish Land Fund for support in meeting the purchase price and employing a part-time member of staff. Other funds will come from applications to charitable trusts and the Scottish Government, a community share issue and our own resources. We have a clear idea of the costs of the building refurbishment and the replacment of the fuel pumps with card payment models. Support to install charging points will be our other target for the early stages after our community purchase and there are several possible sources of funding.

Longer Term Goals

The move away from fossil fuels is envrionmentally and socially necessary. Climate change is driving a rise in the number of destructive weather events - Storm Eowyn resulted in a five-day power cut for the district. Our scattered population has a very high percentage of older people and the lack of power and communication was very concerning for them. In bringing the petrol station to community ownership we are not blind to the impact of carbon emissions and their effect on community resilience and environmental sustainability.

Although it may seem paradoxical, our purchase of the petrol station will help in lowering carbon emissions by removing the need for unnecessary journeys of around 50 miles. It will protect local services by keeping a point of sale in the area. It will make the district more secure in providing a storage space for emergency resilience supplies (like camping stoves and satellite phones to be used in future storms). It will allow us to install charging points and solar panels. It will bring a restoration of the adjoining pier into consideration as a tourist and leisure resource for swimming and boating. It will give us a site to base the community transport project that was viewed so favourably in our 2023 community survey. All of these achievable goals mean that the community buy-out will be benefiting the area long after the need to sell fossil fuels is gone.

No supports
20221027_111318 (1).jpg

Complete our lifeline link road!

2025-06-02  •  No comments  •  Isle of Kerrera Development Trust  •  Regeneration Capital Grant Fund

In 2021 and 2022, IKDT secured funding to construst 1.79KM of brand new road connecting the North and South of the island. This project has been in the pipeline for many decades and has connected up the two different communities and is allowing our island to thrive as one. Just after we have secured the funding for the 2nd stage of the project, the tar topping, war broke out in Ukraine. Apart from the obvious humanitarian crisis, this had an instant impact on the price of all the raw materials required for surfacing. It meant we had to scale stage 2 back and make do with tarring the new built section of the road with a single layer of tar and leave approx 500 metres of road in an unbound, farm track state. Our plan for stage 2 had been to deliver 2 layers of tar over the new road (1.79km) and the 500m of existing road when we could petition the council to adopt the road as it connects up the existing council road to several council tax paying households. As it stands, while the road is in use and is hugely beneficial to life on the island however the maintenance burden on IKDT is not ideal. The council will not consider adoption until the road is brought up to the standard we had planned for stage 2 so we are hoping to complete the job. Adoption is key to the long term future of the road and indeed to whole community as it will allow unfettered access to all including vital services, emergency vehicles and access to the lifeline ferry service. The surfacing could be delivered in one week but the effects would be felt for generations to come. We would hope to continue the excellent working relationship with A&B Roads department to help deliver the best value for money possible.

No supports
Dunoon Skatepark.jpg

Dunoon Skatepark Redevelopment

2025-05-30  •  No comments  •  Dunoon Community Development Trust  •  Regeneration Capital Grant Fund

Dunoon Community Development Trust wants to work with children and young people to design and develop a new skatepark facility in Dunoon that will better meet their needs and encourage increased outdoor activity and community connection.

Dunoon Skatepark is sited in Ardenslate, one of two areas in the town within the highest decile of the Scottish Index of Multiple Deprivation.  The original skatepark was campaigned for and developed by local young almost 20 years ago and its creation was a major achievement for those involved. It was well used for several years, however, the original steel structures and rough surfacing are no longer fit for purpose and levels of use have seriously declined. Some elements of the facility present a significant hazard, especially for learners, so there are very few younger users or family involvement. Local young people and young adults have been actively involved in campaigning for improvements to the skatepark gathering hundreds of signatures on their petition on Change.org  Recent engagement with school pupils has confirmed their interest in improved facilities for skating and wheeling on the site.

By developing this facility to better meet the needs of skateboarders, in-line skaters and BMX bikers of all abilities, we will be able to support and encourage children, young people and young adults to build their skills and enjoy peer-to-peer learning experiences. More time spent outdoors engaging in interesting physical activities will help to address the health and wellbeing challenges faced by young people and young adults and help to reduce social isolation.

This project will run for between 12 and 18 months including consultation, design, planning, permissions and construction.

The skatepark is situated on land owned by Argyll & Bute Council so it will be vital to work in partnership with them. Consultation will also involve local schools, Dunoon Community Council and Live Argyll youth work team.

No supports

Sonas Childcare Project

2025-05-26  •  No comments  •  South Islay Development  •  Regeneration Capital Grant Fund

SID plans to build a dedicated childcare facility to cater for babies and toddlers up to three years old and provide dedicated childcare services for the community. This building will complement the soon to be finished new community Pavilion, and will be set within the 16 acres of Playing Fields, with access to a nearby enclosed playpark, and plenty of green space. 

On Islay there are a very limited number of childminders available. Islay has had a steady number of babies born in the last three years (ranging from 20-22 babies/year) and this is predicted to rise. Due to the lack of services available, families are using relatives and friends as childminders to allow them to return to work. The provision of a dedicated childcare facility would provide flexibility with this.

The facility will bring the following positive changes: 

  • More flexibility for families with regards to 0 to 3 childcare options.
  • More opportunities for families to work childcare around their needs, enabling parents to return to work. 
  • Families may be encouraged to move to Islay, as instead of having severely limited childcare options there will be a dedicated facility. 
  • It will provide options for employment and training within the facility. It may help provide an opportunity for students and school leavers to gain work experience in their chosen field, without having to leave Islay. 

It is anticipated that it will be several years before the facility is up and running. The project is currently in the early stages. A Planning Application has been submitted to Argyll & Bute Council, and the Building Warrant has been completed as far as possible, given the current funding restrictions. SID are currently looking for funding to finalise the Building Warrant, and move on to the construction phases. 

No supports
Ceilidh in Hall.jpg

Redevelopment of Tayvallich Community Hall

2025-05-28  •  No comments  •  Tayvallich Community Hall SCIO  •  Regeneration Capital Grant Fund

What we want to do - 

Phase 1 involves replacing the hall disabled access and the provision of a generator to enhance community resilience. 

Phase 2 re-configuring the toilet block and the provision of hot water in the ladies toilets.

Phase 3 - installing a decking, and two patio doors to enhance provision for events. Also creation of more storage. 

Why our project is needed. 

The hall is used by the local primary school for provision of sports facilities and other activities. The Parent Council arranges parties and other communal events - such as an annual car wash and wreath-making at Christmas. The hall provides many family events, shows, films and talks - to keep the local community informed and entertained. A seperate gym club runs on a wednesday. The multi-sport court provides for sporting activities such as hockey and tennis, and the playing field is used for football and field sports. 

Many tourists use the hall's facilities especially for events such as "Gala day", and tourism is an important industry in Scotland. The hall was instrumental in the creation of Tayvallich Initiative which aims to provide low-cost housing in the village for essential workers and implements "rural burdens" which help ensure community survival longer-term. The annual Kayak Symposium run by local firm "Argyll Kayaks", brings dozens to the village for a weekend, centered around the hall, which benefits the whole community including the community shop and the Inn. 

"Resilience Planning" is a recent aim of the Community Hall. A few months back there was a power outage for 4 days - many were caught out by it. Apart from losing heating and cooking, many have private water supplies (pumped) and so had no water either. The hall did its best as a "resilience hub" but had no electric itself - simply brewing hot drinks on a gas stove - it could not offer shelter/heating/lighting/hot food. Resilience planning involves a back-up generator to better serve the community in such future events. 

The hall provides many services to the local community. Yoga on a monday and thursday; table tennis on a monday; bowls on a thursday; "Pickle ball" on a tuesday; "stretch and tone" on a tuesday; Fencing on a wednesday; Lunch Club every month - providing for the retired members of our community. The hall also hosts First Aid classes which benefit the local community and beyond. 

The hall is also a popular venue for weddings (and funerals). There are regular Coffee Mornings in aid of a range of charities - Beatson cancer charity; the Lochgilphead Snowdrop Centre; and the Taynish run in aid of McMillan cancer care. The annual flower show is also a popular event. In addition, the hall hosts events such as Films and Talks - often being full to capacity. Friday and saturday evenings often see the hall host Bands and Ceilidhs which attract visitors from further afield. It encourages and supports local artists and musicians. 

The project will bring about many positive changes.

It is essential that the hall can continue to act as a community hub. Phase 1 - the generator - will ensure it can run as a resilience hub too. Phase 1 also includes better disabled access which is essential. Provision of better toilet facilities is also essential (Phase 2), given the hall's popularity. Phase 3 will increase the capacity of the hall - even more community activities will be encouraged and supported. 

The hall is a vital community resource and needs to be supported and protected. The success of the community hall helps kindle social cohesion - it is a vital part of village life.

The project will start in July 2025 and take 6 months to complete.  

No supports
Old forestry buildings

Creating a Cairnbaan Community Hub. Refurbishment of the old forestry buildings

2025-05-30  •  No comments  •  Cairnbaan Community Trust  •  Regeneration Capital Grant Fund

1. What we want to achieve.

The Cairnbaan Community Trust, (SC052905) wants to refurbish the forestry buildings to provide a community gathering point and flexible workshop and event spaces. We want a community hub that can be used by the community for education such as crafts and Gaelic, health e.g. yoga and other activities, recreation and social gatherings, inside and outside and temporary office space for local entrepreneurs.

Our priority is the smaller of the two buildings which will provide space for community events and workshops, social meeting space, hot desks and a community kitchen. There is external space that can be developed to provide a community garden and outside event space.  It is hoped in the future the larger of the two buildings can be developed to provide space for larger workshops and events.

We have divided the work into phases and we are currently seeking funding for phases 1 and 2. 

Phase 0: This covers the procurement of the forestry buildings under a community asset transfer funded by the Scottish Land Fund and we have secured initial funding for essential repairs to both buildings to make them safe and weatherproof.  The work will start when we take ownership on the 01/08/2025.

Phase 1: Is the refurbishment of the smaller building.  This phase will change the internal layout of the building to create flexible spaces.  This entails new partitions, doors, lighting and upgrade to the heating.  Additional facilities, external and internal, will be needed for disabled and users with special needs.  We also aim to fit a community kitchen and social space for coffee mornings.   Finally we need to replace windows and install new furnishings and fittings.

Phase 2: Is the landscaping and provision of a community garden and outdoor space.   

Phase 3: Is the refurbishment and fitting out of the larger building.  In this phase we also plan to look at energy efficiency improvements, e.g. heat pumps and solar panels.

2. Why our project is needed

Currently there is no community centre to provide a focal point or resources for the community.   There is a risk of social isolation amongst our older population and there are no facilities for the young people in our village.  Community cohesion is being eroded.

We commissioned a feasibility report through Community Enterprise which highlighted the following points. Accessing facilities is difficult without a car, the minimal bus service is a school service with no evening or Sunday services.  There are no shops, medical or other services in the village.  Despite scoring highly in other domains the area falls into the 10% most deprived areas in Scotland in terms of access to services in relation to the Scottish indices of multiple deprivation. Feedback from local people highlighted that a primary need in the community is an indoor social area and meeting space.

3. The positive changes our project will bring

Our vision is to reduce isolation, improve community life and reflect the cultural, environment and historic heritage of the area. The current priorities for the CCT are.

  • Bringing the community together to enable opportunities for social interaction and growth.
  • Advancement of arts, heritage, culture and science.
  • The provision and organization of recreational facilities to improve the quality of life for the community.
  • Improving the environment including education about the environment, culture and history.
  • The relief of thos in need either because of age, ill health, disability or financial hardship.

The refurbishment of the buidings will provide a focal point for the community and the resources to bring the community together especially those that feel isolated. It will provide resources for all ages across the community and give everyone opportunities for development and a sense of purpose and indentity.

Through current engagement with the local community we have already identified skills and volunteers that can contribute to the refurbishment which will foster community involvement from the outset

4. How long will our project run

Phase 1 and 2 of the project will start on: 05/01/2026

The project will run for: 15 months

Our Business plan and the Feasibility report are available on request.  Unfortunately the file size was too big to attach.

No supports
The Atlantis Leisure Centre in Oban

Renewing the fabric of Atlantis Leisure for the next Generation

2025-06-02  •  No comments  •  Atlantis Leisure  •  Regeneration Capital Grant Fund

Atlantis Leisure is a vibrant, community-run health and wellbeing hub in the heart of Oban. For over 30 years, we’ve been a lifeline for locals of all ages - a place where toddlers learn to swim, teens train with sports clubs, adults improve their fitness and older residents stay active and connected. As a registered charity and social enterprise, every penny we earn is reinvested. Our huge range of facilities are designed to support active, healthy lives. We work with schools, NHS partners, and community groups to deliver inclusive, high-impact services. With over 150,000 visits a year and no other facility like it for 95 miles, Atlantis isn’t just a leisure centre - it’s the beating heart of our community.

This application comprises separate projects that are also listed on Aspiring Places indivdiually but we thought it made sense to group them together as a single proposal for the purposes of RCGF too:

1. What do you want to do? We propose a multi-strand capital regeneration programme at Atlantis Leisure — a vital, community-owned asset serving Oban and surrounding remote rural areas — to deliver large-scale, community-led change aligned with RCGF's aims that breathes new life into an over 50 year old facility. 

This project brings together three deliverable, community-prioritised infrastructure improvements:

  1. Installation of rooftop solar panels and battery storage: significanty reducing carbon emissions, lowering long-term operating costs and contributing to Net Zero targets. 160k
  2. Expansion of Atlantis’ gym: a two-storey extension to accommodate growing community demand, support inclusive programmes like Elevate & Stay Active, and provide flexible meeting and office space to host outreach services and community partners. 175k
  3. Creation of accessible changing facility: reconfiguring existing internal space, to provide a dignified, fully inclusive changing area to support disabled users 50k
  4. Restoration of end of life outdoor sports pitch: bringing an end-of-life, unusable asset back into service, enabling schools, clubs, and informal groups to use it year-round, relieving pressure from indoor space and boosting physical activity levels. 90k
  5. Restoration of Sports Hall Roof: rectifying end-of-life aspects of the roofing. 150,000k

2. Why is your project needed? Atlantis Leisure is a community-run registered charity and social enterprise that delivers year-round access to sport, physical activity, and wellbeing services. We are the only such facility within a 95-mile radius and serve over 150,000 users annually — yet key parts of our infrastructure are now limiting access, affordability, and impact.

  • The pitch is end-of-life and unusable, with back-up facilities constrained by a statutory noise order.
  • We've run out of room in our existing gym facility meaning vital communtiy programmes like Healthy Options are unable to operate properly
  • There is no suitable changing space for users with complex access needs, meaning many are excluded from participation.
  • Energy costs are surging, making it harder to deliver affordable access and sustain services for low-income families.

The project will regenerate these essential community assets, futureproof our building, reduce inequalities in access, and enable Atlantis to deliver sustainable social value for decades to come — directly supporting the RCGF’s priorities around deprivation, climate, inclusion, and place-based transformation.

3. What positive changes will your project bring about?

  • Inclusive Infrastructure: The accessible changing space addresses long-standing inequality, empowering disabled users to participate fully & independently.
  • Net-Zero Progress: Solar & battery systems will directly reduce carbon emissions, support national climate goals, & make Atlantis more financially sustainable.
  • Renewed Community Space: The front pitch transformation will reinstate valuable outdoor capacity, expanding options for schools, clubs, and families.
  • Address Capacity Issues: Expanding the gym answers a growing problem with existing capacity.
  • Child Poverty Impact: Reducing running costs helps us to maintain subsidised programmes, removing financial barriers to physical & social wellbeing.
  • Place-Based Renewal: This project aligns with the Place Principle and National Strategy for Economic Transformation by investing in a community-anchored asset with cross-cutting impact.

Together, these outcomes represent transformational, community-led regeneration that will enhance the resilience, health, and wellbeing of Oban.

4. How long will your project run for?

The project is fully deliverable within FY 2026–27.

  • Start: Early 2026
  • End: March 2027
  • Drawdown Ready: All spend will be committed or completed within the terms of the RCGF.
  • Delivery Approach: Projects will be managed by Atlantis Leisure’s Facilities Subgroup with oversight from the Board. 
  • Match Funding: Confirmed: Atlantis own contribution. Pending: we are actively pursuing applications and conversations with other funders including LES's CARES programme

No supports
The Harbour and ASH

Lighting Up the Shore Station - a sustainable Hub for Tiree

2025-05-27  •  No comments  •  Hynish Trust  •  Regeneration Capital Grant Fund

1  We would like to refurbish Alan Stevenson House (ASH) to offer a locally inspired restaurant, bar with 6 ensuite rooms (1 disabled).  We would like to upgrade the Harbour with pontoons and seating/viewpoints to take in the wonderful natural environment and encourage people to come by boat to the site in the summer months.  Morton Boyd Hall (MBH) is an excellent multi purpose facility that just needs some upgrading and could complment any activities going on at the site.    The site at Hynish, with its heritage and special quality of place, has the opportunity to develop its local hospitality and develop something of a Hub for the southern end of the island.  Capturing tourism and events spend, alongside island/day visitor spend would provide a revenue stream.

2  The Skerryvore Shore Station was transferred to the Tiree community in January 25.  The transition has taken 3 years.  There are 3 income streams - Housing, Heritage and Business -  that will ensure it is a sustainable community organisation going forward.  We have been reviewing the use of our 20+ A listed buildings to ensure they are fit for purpose and revenue earning where possible.   ASH was first rebuilt in 1990 as a hostel type accomodation for groups with special needs.  it was only used for a few weeks in the summer months and was always a overhead for the charity.  MBH had been used to house the exhibition/museum but originally had been rebuilt as a multi purpose hall.  The harbour stands strong against the incredible tides and weather.  It is a viewpoint for sealife and birds.  The community when asked what they would like to see at the site in our survey and subsequent community events were clear that Business should be a priority.   84% said that they wanted a restaurant/cafe, quality accomodation and event space all year round.  They also wanted the Harbour preserved.  So our community mandate was clear.  We have piloted the restaurant and rooms over the past 2 years and now believe that it could definately work if we had a good standard of accomodation to offer and a multi purpose space for events.  We have moved the exhbition to another building to free up Morton Boyd Hall so that we have a this multi purpose facility.  We will then be able to work with community groups to put on a variety of events and functions during the year.  We will also be able to provide permanent employment for locals.

3  We can already see from our pilot that our community is very positive about the fact we have a local family working at ASH and have created year round employment for locals.  We have trialled a number of community events over last winter and they proved to be very popular.  The Tiree people just love the shore station and feel a strong sense of guardianship.  The pilot has also showed us that we could have a reasonable income stream from this.  We now have some facts and figures to base our projections on which gives us confidence this is the right way forward.  All the buildings at Hynish need to work and complement each other to ensure the "place" is kept in alignment.  The pilot has demonstrated that the restaurant/rooms/bar and events do contribute greatly to this.  The project would enhance the employment opportunities; keep a family with 3 children living on Tiree as they have jobs; provide the much needed income stream to ensure sustainability; reduce running costs; make the buildings all more energy efficient and in line with our aim to lower the carbon footprint and provice a place for people and business to floutish.

4  The project will start early in 2026 and be completed by November 2026.

No supports
Upper Square from the rear

Lighting up the Skerryvore Lighthouse Shore Station - The Lighthouse Cottages

2025-05-30  •  No comments  •  Hynish Trust  •  Regeneration Capital Grant Fund

1  We need to repoint the external stonework and do work on the chimneys and roof of the 4 lighthouse cottages.  No maintenance work has been done for many years and there has been major issues with damp and water damage in these 4 properties.  There is a critical housing shortage on Tiree and in particular affordable housing.  We have now 2 of the cottages on long term lease to locals and would like to make the other 2 habitable for long term lease.  We would also like to use this opportunity to encourage young people on Tiree to consider construction and in particular stonemasonry as a possible career.  The team we would use, have experience of running training programmes for school pupils to come and work on the site and learn some of the basic skills of maintainting heritage buildings.  This added value to the project would bring a very useful experience to our local children who are disadvantaged at present from these type of careers activities.  We would also offer to design a long term training programme for a local person so that we could have local skills to maintain the A listed heritage buildings on our site.

2  We funded work late last year on two of the chimneys by a stonemason specialising in these kind of listed buildings.  He has advised that all the external walls, chimneys and roof require work done to preserve these wonderful buildings. The work he did was enough to sort the immediate issues of dampness coming from the chimneys.  There is still some damp coming through the walls/windows.  Also the other chimneys that we did not repair mean that two of the cottages are not fit for long term lease at the moment.  Funding has been recieved by Argyll and Bute Council to allow us to the internal upgrading but we require major funding for all the external works so that we an offer 4 good quality upgraded affordable homes for locals.  One of the issues has been lack of maintenance of all the A listed buildings on our site.  There has been some repair work done but it has exaccerbated the problems due to lack of knowledge.  These buildilng require specialist skills.  If we can train up someone locally to do the basic ongoing maintenance through this project this would be of huge long term benefit to the Hynish Trust.  

3  When we advertised the last cottage for lease we got 5 applicants.  They were all local people wanting to come to live at Hynish.  Our vision is to create a clachan type village at the Skerrryvore Shore Station in Hynish for people to live, play, learn and enjoy.  The demand is there amongst the community for long term affordable housing and this is a relatively quick win to maintain the two leases we have and create another two.  But more importantly to ensure the buildings are presrved for the long term future.  So the refurbishment of the externals of these buildings would be transformational for the Hynish Trust.  It would ensure that these buildings will be fit for purpose for the future.  It also addresses the critical housing situation.  Providing an opportunity for local children to experience somehting different as a possible career opportunity would be welcomed by the school and the community.  If we can also get a local person trained up to be able to maintain all our buildings externally this would be a long term benefit to the community and create much needed local employment.

4  The project would start in March 26 and run to September 26.

 

 

 

No supports